TGC-1 Plants in St. Petersburg Turned to Periodic Heat Delivery Mode
OREANDA-NEWS. Starting from 00:00, September 20, 2016, in accordance with the order of the Energy and Engineering Committee under St. Petersburg Administration, energy facilities of PJSC TGC-1 will operate in a periodic heat delivery mode.
Educational, health care and social protection institutions are being currently connected to the nine CHPPs in St. Petersburg.
To provide continuing heat supply by the plants in the heating season of 2016-2017 the Company specialists performed all the required preventive maintenance and adjustment of heat supply systems. The following works were completed in summer: overhaul of turbine units at Centralnaya, Yuzhnaya and Severnaya CHPPs, overhaul of boilers at Avtovskaya, Vasileostrovskaya, Yuzhnaya and Severnaya CHPPs, as well as routine inspection and renewal of auxiliary equipment - cooling towers, chimneys, storage tanks and fuel oil tanks.
Комментарии