The main component of CDU / VDU-6 unit Was Mounted at TANECO
The equipment manufactured by JSC "Volgogradneftemash» was delivered to Nizhnekamsk by waterway in November of the current year. Because the tower’s size and dimensions (weight - 287 t, height - 40.5 m) they had to perform a serious logistical operation for the transportation of the tower from the Nizhnekamsk cargo berth to the construction site.
New engineering solutions were also required for construction of a 17-meter foundation, which has become a reliable pedestal for the vacuum distillation tower.
The large-tonnage equipment installation was preceded by a serious preparatory process involving URPS of PJSC TATNEFT, JSC TANECO and OOO SOPiG, which is the executor of the installation works.