OREANDA-NEWS. Based on the most important tasks for the unconditional implementation of the major priorities of the development of the economy as defined by the President of the Republic of Uzbekistan at the session of the Cabinet of Ministers dated January 15, 2016 JSC "Uzbekenergo" is taking the necessary measures to ensure the sustainable operation of energy enterprises, achieving the forecast parameters of production activity in 2016.

At the end of the 1st quarter of 2016 achieved reduction of production costs by 102.3%. The production growth rate of marketable products amounted to 106.3%. Implemented supply of electric energy in the amount of 12.1 billion. KW per/h. Released thermal energy in the amount of 2.5 million. Gcal

In accordance with the Decree of the President of the Republic of Uzbekistan dated December 25.2015. № DP-2458 "On investment program of Uzbekistan for 2016" are being implemented 23 large investment projects to create new, modernization and reconstruction of existing facilities. In the current year provided input 5 objects.

The project "Expansion Talimarjan TPP with the construction of two combined cycle power plants with a capacity of 450 MW," being installed HRSG units, auxiliary equipment of the gas turbine and the lower part of the steam turbine, as well as preparatory work for the installation of a steam turbine generator installation and assembly of power transformers. On the platform delivered steam turbine generators for combined cycle-1, PSU-2 gas turbines for PGU-1.

According to the project construction on the Angren TPP power unit capacity of 130 - 150 MW district heating selection for burning high-ash coal are conducted installation and commissioning of main equipment, completed in full the construction of infrastructure facilities, the construction of the main building, the boiler building, the steam turbine, cooling towers, etc.

According to the project of building a new thermal power plant with capacity of 900 MW, consisting of two blocks of combined-cycle plants for 450 MW in Turakurgan district of Namangan region held tender bids for a general contractor on a "turnkey". At the construction site civil works are conducted.

According to the project "Construction of two combined cycle power plants with capacity 230-280 MW Takhiatash TPP" is currently going evaluation of tender bids for a general contractor.

According to the construction of a solar power plant of 100 MW in Samarkand region completed an assessment of technical and financial bids for a general contractor company, the results are approved by the ADB.

According to the project "Construction of external power supply for traction substations under construction electrified" Angren-Pap "railway line is an extension of 110 kV switchyard, reconstruction and construction works on the SS-Obi Hayot 110/220 kV. To date, completed work on the reconstruction of the existing 220 kV overhead line at the intersection of the railway road, mounted the support and made of wire installation.

According to the project "Construction of external power supply of traction substations of electrified railway line under construction" Samarkand - Bukhara "works on reconstruction of HVL 110-220 kV.

According to the project "Construction of the connecting electric networks on construction enterprises in the PPE" Angren "and PPE" Jizzakh "carried out design and survey works and started construction and installation work.

According to the project "Organization of production of overhead line fittings and insulators» JV «Armaturno-izolyatorniy zavod» performed recon-struction of the building for production and work on support structures on the territory of PPE "Angren".

As a result of the industry of the enterprise for the introduction of modern electronic devices of electric energy for the past since the start of the implementation period established by legal consumers 234.6 thousand units of three-phase, 162.1 thousand units of single-phase electronic electricity meters..; at residential consumers 29,7 thousand. pieces of three-phase, 3 995.6 thousand. pieces of single-phase electronic electricity meters.

Set of measures to increase the use of alternative sources of energy, provides the introduction of solar collectors for heating and hot water for industrial and domestic buildings, regional electric grids enterprises. At this stage, we contract with JV " Solar heat energy " for the purchase of solar collectors and the work is carried out according to the signed contracts .

In order to implement the decision of the President of the Republic of Uzbekistan dated February 09.2016. № DP-2487 "On State program " Year of a healthy mother and child " by JSC" Uzbekenergo "sectoral program is designed to forecast costs in the amount of 35.9 billion. UZS, formed a committee to ensure the implementation of activities. The costs of implementing measures on the sectoral program "Year of a healthy mother and child" in the 1st quarter of 2016 amounted to 4.5 bln. Soums or 100% of the forecast period.

As part of the Food Programme continued work to increase the volume of agricultural production.

As of April 1, 2016 the total number of livestock contained in the enterprises of the sector is 2 333 heads, including 1530 heads of cattle and 803 head of sheep and goats.

During the 1st quarter of 2016 it produced 6.0 tons of meat, 195.9 tons of milk, 90.4 tons of dairy products, 3.4 tons of vegetables and 0.2 tons of marketable fish.