IDGC of Centre, PJSC held a meeting of the Board of Directors, the adjusted Investment Program for 2016-2021 was approved
The indicators of the Company’s adjusted Investment program for 2016-2021:
Planned period: |
2016 |
2017 |
2018 |
2019 |
2020 |
2021 |
||
---|---|---|---|---|---|---|---|---|
Capital investment, mln RUB VAT exclusive |
Approved plan* |
13 387 |
13 941 |
14 697 |
15 187 |
16 057 |
||
Adjusted plan |
13 244 |
13 941 |
14 699 |
15 190 |
16 061 |
16 658 |
||
Financing, mln RUB VAT inclusive |
Approved plan* |
16 194 |
16 418 |
17 375 |
17 911 |
18 968 |
||
Adjusted plan |
14 294 |
16 418 |
17 375 |
17 911 |
18 968 |
19 606 |
||
Commissioning of Fixed Assets, mln RUB VAT exclusive |
Approved plan* |
13 694 |
14 199 |
14 932 |
15 593 |
16 043 |
||
13 623 |
14 365 |
15 107 |
14 936 |
16 221 |
17 254 |
|||
Commissioning of capacity |
MVA |
Approved plan* |
803 |
739 |
854 |
1 049 |
573 |
|
Adjusted plan |
834 |
851 |
923 |
763 |
608 |
352 |
||
km |
Approved plan* |
4 200 |
4 394 |
4 773 |
4 438 |
5 819 |
||
Adjusted plan |
3 550 |
4 222 |
4 425 |
4 308 |
5 160 |
4 821 |
* The Investment Program of IDGC of Centre for 2016-2020 was approved by the Company’s Board of Directors (Minutes # 05/15 of 13.03.2015) and approved by Order of the Ministry of Energy of Russia dated 14.12.2015 № 951
The funding of the Company’s adjusted Investment Program for 2016-2021 at the expense of the Company’s own funds will amount to 90%, - (including 65% - depreciation). The Investment Program financing through borrowing will be 10%.
More than 56% of the financing of capital investments is planned to be spent on modernization and reconstruction, the remaining 44% on new construction and expansion.
Priority projects as part of the Company’s Investment Program for 2016-2021 are as follows:
- reconstruction of the 110/10 kV Substation "South" to restore life of fixed production assets and liquidation of power shortage;
- reconstruction of the 110 kV Substation "Korocha" with relocation of the substation to a new site to restore life of fixed production assets and expand the electricity distribution market;
- construction of the 110 kV Conductor Frunze - Malinovka - Red Yaruga to improve the reliability of power supply;
- reconstruction of the 110 kV Conductor "Mtsensk-Chern", "Mtsensk-Plavsk" to ensure the specified level of reliability and increase transmission capacity of the lines.
Implementation of the Investment Program will allow IDGC of Centre to fulfill its commitments to improve the quality and reliability of electricity supply in the framework of the Strategy of development of electric grid facilities of the Russian Federation.