ARMZ: Installation of crushing and screening plant completed on coal yard of PIMCU’s Urtuyskoye Mine Office
OREANDA-NEWS. Putting the plant into operation will allow to improve product quality and expand product range through high-performance coal crushing and screening. "Accurately complying with requests of our partners, we will be able to significantly increase the number of consumers of Urtuyskoye coal. The crushing and screening plant will help us deliver high quality products through sorting coal by fractions, which, by the way, gives at the same time an increase of combustion value and moisture reduction. We plan to export 20-50 mm coal fraction, and supply 50-300 mm fraction to domestic consumers. The so-called tripping coal - 0-20 mm - will be delivered to Krasnokamensk CHP,"- says Andrei Prostakishin, Commercial Director of PIMCU.
The project cost is about 120 million rubles. Today the plant has been put into commercial operation. All conveyors, crushing unit, coal classifying screen, vibrating feeder have been assembled. The works to build retaining wall of the coal yard and basement for dump trucks access to unload coal in the bin have been completed.
All assembly and preparation works were performed by employees of PIMCU’s subsidiary – SSRT LLC.
Комментарии