Installation of control cabinets has started in the control building of LAES-2
The specialists will have to install about 300 units of equipment. The weight of each cabinet is about of 500 kg.
Installation of the equipment is carried out at levels +8.000 and +15.000. Lifting to height is executed by means of a load-lifting mechanism located in a lift shaft. For convenience and safety of installation, Specialists of JSC “SOSNOVOBORELECTROMONTAZH” are using a special pull-out platform. It is used to move the equipment from the shaft, and to transport it further, to the installation zone.
After installation of the equipment, they will start to connect it to the power supply system.
The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.
The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.