In turbine building of first power unit of LAES-2 generator stator installed
The equipment weighing 440 tons was lifted from the level 0.000 to the level +16,000 by means of an overhead crane and was installed in the machine hall. This critical operation was performed by specialists of sector no. 6 of JSC "MSU-90".
Lifting of the stator was preceded by long and thorough preparation. The overhead crane, which was used to install the stator to its regular place, had gone through a long modernization process: further development of various parts, mechanisms software was performed. In order to test the crane, specialists of “TITAN-2” holding have developed and manufactured a steel basket simulating a load of the stator on the lifting mechanism.
After installation the generator stator to its regular place, they will start its further assembly and connection with the turbine. Then specialists will perform tests and start-up and adjustment works. Installation of the stator will also enable to continue works on alignment of the turbine shaft line, centering and setting of rotors.
The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.
The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.
Комментарии