GE’s steam turbines to boost capacity of West Damietta and Assiut Power Plants to 2.25 GW through combined-cycle operation
Dr. Mohammed Shaker, Minister of Electricity of Egypt, said: “The shift from single-cycle to combined-cycle operation at the West Damietta and Assiut Power Plants is a key part of our strategy to enhance operational efficiency and strengthen generation capacity. Both power plants already help meet peak summer demand as part of our Power Boost Program and now the planned upgrade will help enable the power plants to be even more efficient, sustainable and productive.”
West Damietta and Assiut Power Plants are part of the mega-deals signed by GE earlier this year as part of its commitment to the country to strengthen energy sector efficiency and boost power production. At the Egypt Economic Development Conference, GE had announced its support to the ‘Egypt Power Boost Program,’ by helping generate the 2.6 GW of electricity, the amount equivalent to the power needed for approximately 2.5 million Egyptian homes.
Mohammed Mohaisen, President & CEO, GE Power Generation Products Middle East and North Africa, said: “The enhancement of the West Damietta and Assiut Power Plants underlines the focus of the Egyptian Ministry of Electricity to implement energy efficiency measures that add to the power capacity and help meet growing demand for power for household and industrial use. We are committed to supporting the Ministry in fulfilling the Egypt Power Boost Program through such advanced technologies and by drawing on our proven expertise. With the two plants already in operation, we will work with the teams to install the steam turbines for a seamless upgrade.”
GE will provide three D200 steam turbines, which will use the waste heat from the gas turbines to generate extra power. West Damietta has four GE 9E gas turbines that generate 500 MW, while the Assiut plant has eight 9E turbines that generate 1 GW. Both plants already contribute to the national grid, as committed to help meet the peak summer demand.
Sofiane Ben Tounes, GE’s President and CEO for North East Africa, said: “With Egypt focused on ambitious economic development programs, helping meet the growing demand for power is imperative to strengthen its all-round competitiveness. The upgrade of the two power plants builds on our commitment to the nation to serve as a technology partner by providing efficient technologies for boosting the energy sector.”
GE’s advanced gas turbines already help generate more than 11.68 GW of electricity. The company is also investing in a new US$200 million multimodal manufacturing, engineering, services and training center in Egypt which will focus on various industries including power generation, renewables, water, oil & gas, aviation and rail transportation.
With 40 years of presence and partnerships in the country with headquarters in Cairo, GE has over 400 employees in Egypt. In other key growth sectors, over 12,600 GE Healthcare technologies are deployed in hospitals across the country.