Northern expansion of the Aktau port is on schedule
Work on the three berths - grain, container and general cargo - has almost been completed. Picked up all six silos grain terminal, the installation of equipment is completed.
The fourth berth - for port fleet - to be prepared by 18 June.
Now the work is done by external power supply. The work on the transfer of the pipeline through the railway line is in progress.
- Steel structures for the main administrative building will be brought to the site on June 25 - the builders say.
The construction of the foundations of the administrative building, the center of sanitary-epidemiological service, inventory storage and garage.
- We try to keep up with the schedule, - said the representative of the general contractor.
The project "Expansion of the Aktau international sea trade port in northern direction" will allow customers to arrange for a new and modern service and increase the capacity of Aktau port up to three million tons of dry cargo and 1.5 million tons of containerized cargo.