UD Ministry targets generation of 100 MW of solar power in 2 years
As per the MoU, CPWD would provide 629 buildings owned and maintained by it in 18 states for installing solar photovoltaic projects on rooftops by the executing agency SECI for generation of power. A total roof area of 16,76,233 sq.mts is available on these buildings out of which 60% would be used for power generation. Solar panels would be connected to the grid.
To begin with, 1 MW capacity solar panels each will installed over central government buildings in New Delhi like Nirman Bhawan, Krishi Bhawan, IP Bhawan, Vidyut Bhawan, Shram Shakti Bhawan etc., within 6 months. CPWD has installed 930 kw capacity on Indira Paryavaran Bhawan and Nirman Bhawan in New Delhi so far.
Speaking on the occasion, Shri Venkaiah Naidu and Shri Piyush Goyal have lauded the initiative and said successful implementation of this mission would be a trend setter.