KazTransOil completes reconstruction of trunk pipelines Ozen – Zhetyibai – Aktau and Kalamkas-Krazhanbas-Aktau
"KazTransOil" JSC informs about the completion of Uzen – Zhetybai – Aktau trunk
pipeline reconstruction project and the completion of second phase of
Kalamkas – Karazhanbas – Aktau trunk pipeline reconstruction project
"KazTransOil" JSC informs about the completion of Uzen – Zhetybai – Aktau
trunk pipeline reconstruction project and the completion of second phase of
Kalamkas – Karazhanbas – Aktau trunk pipeline reconstruction project
(Karazhanbas – Aktau section).
The project of Kalamkas – Karazhanbas – Aktau and Uzen – Zhetybai – Aktau
pipelines' reconstruction was initiated in conjunction with the planned
redirection of Buzachi crude oil to Uzen HOPS (except that volume of oil
designated for processing at Aktau Bitumen Plant) as well as in order to provide
transportation capacity for future production at new fields at Kazakhstani
sector of the Caspian sea."KazTransOil" JSC conducts the reconstruction project
in three phases that are scheduled for 2014-2017 period. The project includes
the reconstruction of selected sections of Kalamkas – Karazhanbas – Aktau and
Uzen – Zhetybai – Aktau pipelines in order to ensure reliable and uninterrupted
transportation of Buzachi crude oil from Aktau to Atyrau.
The 1st phase of the project included the replacement of 14 km of Kalamkas –
Karazhanbas – Aktau pipeline (Karazhanbas – Aktau section), the replacement
of 25 km of Uzen – Zhetybai – Aktau pipeline and reconstruction of 78.6 km of
Zhetybai – Aktau section of pipeline. The State commission signed the Act of
commissioning of the reconstructed facilities on August 27, 2014.
The 2nd phase of the project included the replacement of 58.85 km of
Karazhanbas – Aktau section and the selective replacement of 60.4 km of Uzen –
Zhetybai section. The State commission signed the Act of commissioning of the
reconstructed facilities on December 26, 2014.
Thus,"KazTransOil" JSC completed Uzen – Zhetybai – Aktau trunk pipeline
reconstruction project. The completion of Kalamkas – Karazhanbas – Aktau trunk
pipeline reconstruction project is scheduled in mid-2015.
The cost of the 1st phase made KZT 13.3 billion and the cost of the 2st phase is
KZT 18.9 billion.