02.12.2014, 20:49
Construction status of 4th Sonyachna Brama complex is updated
OREANDA-NEWS. Fourth phase of Sonyachna Brama residential complex construction status update.
During the period of 1-31 November 2014 construction works at the fourth phase of Sonyachna Brama residential complex (73-79 Lomonosova str., Kyiv) were carried out according to the schedule in two residential buildings.
In building B-6, the following works took place:
- aluminum window panels installation 70% complete;
- facade insulation works 50% (works suspended due to low temperature);
- internal finishing works (wall plastering) - 50% complete (works suspended due to low temperature);
- roof covering 15% complete.
In building B-7, the following works took place:
- construction of the monolith frame fully completed;
- general roofing works - fully completed;
- installation of ventilation, water supply, heating and sewage equipment 90% complete;
- balcony parapets installation - 80% complete.
As reported earlier, TMM commissioned the third phase of Sonyachna Brama residential complex in October 2014.
During the period of 1-31 November 2014 construction works at the fourth phase of Sonyachna Brama residential complex (73-79 Lomonosova str., Kyiv) were carried out according to the schedule in two residential buildings.
In building B-6, the following works took place:
- aluminum window panels installation 70% complete;
- facade insulation works 50% (works suspended due to low temperature);
- internal finishing works (wall plastering) - 50% complete (works suspended due to low temperature);
- roof covering 15% complete.
In building B-7, the following works took place:
- construction of the monolith frame fully completed;
- general roofing works - fully completed;
- installation of ventilation, water supply, heating and sewage equipment 90% complete;
- balcony parapets installation - 80% complete.
As reported earlier, TMM commissioned the third phase of Sonyachna Brama residential complex in October 2014.