CPC Holds Board and Shareholder Meetings
OREANDA-NEWS. CPC-R and CPC-K extraordinary general shareholder meetings and a CPC-R Board meeting were held in Moscow.
The main agenda item of the CPC-R Board meeting was the approval of CPC's 2015 budget.
A CPC Expansion completion schedule with specific commissioning dates was presented to the shareholders for their review and approval.
The extraordinary shareholder meetings elected CPC-R and CPC-K Boards. They also reviewed current business matters and heard an HSE report by the CPC Management.
CPC pipeline system is one of the largest investment projects in the energy industry with participation of foreign capital on the CIS territory. The length of the pipeline connecting the oil fields in Western Kazakhstan with the Marine Terminal near Novorossiysk is 1,511 km. CPC Marine Terminal is equipped with single point moorings which allow for safe tanker lifting at a considerable distance from the shore, also when the weather conditions are unfavorable.
The Expansion Project includes rehabilitation of 5 existing and construction of 10 additional pump stations (2 in the Republic of Kazakhstan and 8 in the Russian Federation), six new storage tanks (100,000 cu.m each) in addition to the existing four near Novorossiysk and a third SPM at the CPC Marine Terminal, and also the replacement of an 88 km pipeline section in Kazakhstan with a larger diameter pipe. The total amount of the Project investments will be USD 5.4 billion.
CPC Shareholders: Russian Federation (represented by Transneft - 24% and CPC Company - 7 %) - 31%; Republic of Kazakhstan (represented by KazMunayGaz - 19% and Kazakhstan Pipeline Ventures LLC - 1.75%) - 20.75%; Chevron Caspian Pipeline Consortium Company - 15%, LUKARCO B.V. - 12.5%, Mobil Caspian Pipeline Company - 7.5%, Rosneft-Shell Caspian Ventures Limited - 7.5%, BG Overseas Holding Limited - 2%, Eni International N.A. N.V. - 2% и Oryx Caspian Pipeline LLC - 1.75%.