MOESK Renovates Electric Grids of Yegor'yevsks District
OREANDA-NEWS. September 16, 2014. In 2014 the power engineers of the Eastern branch of JSC "MOESK" in Yegor'yevsks District of Moscow Region started constructing 10 kV cable-overhead line with the total length of about 12 km. The line, going from substation "Trofimovo", is meant for the power supply of a tele-radio-broadcast center being built in population aggregate Kuz'minki.
Together with it, it will provide an additional reserve of capacity for Kolychyovskiy psychoneurological orphanage. Earlier the power supply of the medical treatment facility was made only from 35 kV substation "Mikhali", what reduced the power supply quality in terms of the power lack. After construction of a new line and reconstruction of the existing grids, the reserve will be also secured from feeding centers "Polbino" and "Trofimovo".
Large-scale reconstruction, aimed at the reliable power supply of settlement Mikhali, is continued at an area of 10 kV OL "Mikhali – Kholmy". Towards the present time at the reconstructed area with the length of over 5 km the obsolete wooden poles have been substituted by the new concrete ones, the obsolete wires – by the modern self-supporting insulated conductor (SSIC). A recloser has been installed – an apparatus which, in case of emergency outages, makes the a feed line sectioning and consumer switching to the standby power supply. MOESK power engineers are finishing the similar works at hard-to-reach areas of the overhead lines from substations "Dvoynya", "Polbino", as well as "Trofimovo", where such important social facilities are situated, as Moscow Regional Mental Health Clinic No.3 and Yegor'yevsky psychoneurological orphanage.
Mikhali – is a dynamically developing settlement, that counts over 200 private housing estates, 20 multi-family dwellings and social support facilities. In the mean time, PTL goes through the forestland, where the main reason of the electric power supply violation of subscribers, was falling down on the wires of trees, damaged by the wood engraver. Before the beginning of the forthcoming autumn and winter period, the specialists plan to expand 27 hectare of forest corridors in Yegor'yevsky district.
Let us specify that the district development (opening of new industrial enterprises, active housing construction etc.) need a provision of the electricity supply of the proper quality. The result of this large-scale work of the power engineers of the Eastern branch of MOESK in Yegor'yevsky district, will become not only the reliability increase of the power supply of its consumers, but as well an opportunity for the subsequent development of the economic potential of the municipality.
Комментарии