National Grid's Engineers Prep for Big Dig on London Power Tunnels
OREANDA-NEWS. National Grid is set to begin the final phase of tunnelling on its flagship London Power Tunnels project.
Manned Tunnel Boring Machine (TBM) Evelyn recently completed a challenging 3.4km stretch of the tunnel underneath the River Thames between Wandsworth and Earls Court.
This involved the twin challenges of digging below the riverbed of the Thames while staying above the path of the proposed Thames Tideway tunnel. Finding a viable route was further complicated by the presence of depressions in the river bed known as scour hollows which are formed by water currents in the river bed above.
Having successfully cleared the Thames Evelyn - which is manned by a team of expert engineers - is now being prepared for the final stage of tunnelling between Earl's Court and Kensal Green. This is due to start in September and is expected to be completed in early 2015.
National Grid Project Manager John Trounson said: "Digging a tunnel under London is challenging at the best of times due to the presence of so many existing tunnels. However going under the Thames brought further engineering challenges which I'm happy to say our expert team was more than capable of dealing with.
"With the Thames behind us we can now look forward to completing the last phase of tunnelling."
Installation of the electricity cables that will transport power supplies across the capital began earlier this year and the project is due to be fully complete and operational in 2018.
Mr Trounson added: "London's one of the world's leading cities and this project will help it maintain that status by helping to keep the lights on."