OREANDA-NEWS. The construction on the Russkaya CS, which becomes a starting point of South Stream Gas Pipeline, is well under way.
LLC "STROYGAZMONTAZH" builds the station by order of GAZPROM INVEST LLC. JSC "Lengazspetsstroy" plays the role of contractor.
1.4 mln m3 soil of required 1.6 mln m3 soil was removed and disposed. The foundation works on main buildings and structures are completed. The installation of process equipment of seven Ladoga-32 GPUs (gas pumping units), related to the 1st and 2nd construction stages, continues. The installation of steel structures of six air cooling units, gas treatment units, captive power plants and boiler houses is completed.
Specialists currently started the installation of enclosing structures of buildings and constructions, interior finishing works, as well as installation of utility networks (water pipes, sewerage facilities, ventilation and heating systems). The construction of off-site and on-site engineering networks is in the process.
On 42 facilities of the Russkaya CS, the works are carried out in strict accordance with the schedule. The 1st stage of construction is to be completed in December 2015; the 2nd one, in December 2016.