IISW Resets in Operation Largest Blast Furnace after Repair
OREANDA-NEWS. The plant's largest blast furnace № 5 of 2300 m3 effective capacity is in operation after it's basic repair has completed at Ilyich Iron & Steel Works of Mariupol, Metinvest group. In all-time period, the unit's ecological equipment has been updated, accompanied with the replacement of the charging equipment and stack lining by advanced method. Investments amounted to over UAH 20 mln.
The repair involved a number of environmental measures which included refreshment of the aspiration system in the stock house, sinter and coke separators and the conveyors “1200” and “1800”.
Now, the furnace is back in operation and its emissions to the atmosphere are reduced significantly.
The new charging equipment was manufactured by Mariupol repair and engineering works. The specialists of this plant performed installation and alignment of the equipment.
The shotcreting technology, implemented during the repair works, provides protection against cracks for the furnace's stack armoring, increased overhaul life and reduced repair cost. Silicon carbide based refractory concrete (spraycast) was applied on to the stack lining with the use of compressed air.
The spraycast is characterized with its remarkable physical properties and is much more resistant to the charge mixture compared with conventional refractory lining. Therewith, shotcreting may be done within three days whereas the lining with refractory materials will take one month or so.
This advanced technology was used twice in the blast furnace plant in 2012. Shotcreting on the furnaces №3 and № 4 has led to reduced coke consumption per ton of pig iron.
Mr. Yurii Zinchenko, General Director of Ilyich Iron and Steel Works:
- Our steelmakers are facing the challenge now present in the country and in the Donbass region. Nevertheless, we keep on making steel, providing people with work and salaries. We continue renovation of production facilities according to our program. All expenses related to the blast furnace №5 are economically sound and will be paid off shortly. The progressive shotcreting technology significantly improves the furnace's stack allows to extend the unit's overhaul life considerably.