OREANDA-NEWS.    Kaluga Turbine Works OJSC shipped a TG 2.5/10.5-K1.4 unit turbogenerator for Chishminskoye Company, part of Sigma Group (Chishmy, Bashkortostan), in May 2014.

The equipment was purchased by the largest agricultural business in the Ural District and the Republic of Bashkortostan. The groupʼs core activities include extraction and sales of vegetable oils and by-products in Russia and also in neighbouring and more distant countries.

The manufactured turbogenerator has a capacity of 2.5 MW. It is intended to provide power for the factory. The unit is easily mountable and supplied 100% prefabricated.

The contract to manufacture the power machine was signed on 29 March 2013. The manufacture took 12 months. Once tested successfully, the equipment was shipped to the customer.