MOESK Supplies GUM with Energy
OREANDA-NEWS. February 24, 2014. The branch of JSC "MOESK" - Moscow Cable Grids has fulfilled its part of the contract as to output of additional capacity supply for heating of premises in the building "Upper Trading Rows" at the Red Square. Upper Trading Rows are the Main Department Store (GUM).
The energy specialists of MCG in a short time built a new distribution transformer substation and transformer substation (DTS and TS); laid a feeding cable line (CL) of 10 kV and 5000 meters in length. In addition, the distribution cable line was laid in length of 1800 meters.
Currently, electrical equipment (DTS, TS and CL) is ready to be put into operation.