OREANDA-NEWS. LLC "STROYGAZMONTAZH" has completed construction and installation works on Novosindorskaya CS, Novoprivodinskaya CS and Novoyubileynaya CS (1st string) as a part of the Ukhta - Torzhok trunk gas pipeline system.

For the moment the start-up and commissioning works are being performed. ZAO Yamalgazinvest is the Customer of the construction.

Four gas pumping units (25 MW each) have been installed in every station, therefore aggregate capacity of each compressor station amounts to 100 MW. All stations have been built according to the schedule of the investor of the construction - OAO Gazprom.