Krasny Kotelshchik Shipped Equipment for CHPP-20 of Mosenergo
OREANDA-NEWS. The Taganrog Boiler-Making Works “Krasny Kotelshchik”, a member of the power plant concern OJSC Power Machines, has shipped the last assemblies of the HRSG for PGU-420Ò of CHPP-20, the branch of PJSC Mosenergo.
A Contract for designing, manufacturing and supply of the equipment was signed in December 2012. The customer is PJSC TEK Mosenergo. The range of products manufactured and shipped by the Taganrog Boiler-Making Works “Krasny Kotelshchik” includes the assemblies of the HRSG of higher erection readiness and also the boiler-auxiliary equipment. Besides, according to the Contract terms and conditions the Company will render services on erection, adjustment, test, try-out, start-up, and commissioning supervision of the supplied equipment.
The HRSG's assemblies of three pressure types are designed via use of up-to-date steam-gas technologies, which will provide high efficiency of electrical and heat energy generation and minimize negative impact on the environment.
The complete shipment of the HRSG has been finished in full. At the moment the additional delivery of the separate items of the boiler-auxiliary equipment is being carried out.
At start-up of the new power unit which is scheduled for December 2014 its installed electric power will amount to 420 MW, heat power - 220 Gcal/h, efficiency coefficient of PGU-420 (in condensing mode) - more than 58%.
Комментарии