SGM Won Contracts to Construct South Stream Trunk Gas Pipeline
OREANDA-NEWS. Corporate Costs Department of OAO Gazprom drew up the results of proposals to perform construction and installation works on “South European Gas Pipeline. Pisarevka - Anapa Section, km 223.1 - km 310, km 310 - km 436 and km 436 - km 570” within “Unified Gas Supply System Expansion for Gas Provision to the South Stream Gas Pipeline” construction project.
LLC "STROYGAZMONTAZH" was recognized as the General Contractor for the facilities construction. The Customer of the gas pipeline is Gazprom invest LLC. Kubanskaya CS - Korenovskaya CS connecting gas pipeline with the length of 57 km will be built as well.
As the Subcontractors for the construction of gas pipeline sections and the connecting gas pipeline were chosen JSC "Lengazspetsstroy", JSC "KRASNODARGAZSTROY" and LLC "SSK "Gazregion".
All the works are planned to be completed by the end of September 2015. Drilling and blasting operations on rocky grounds as well as the necessity to cross paddy fields area make the project implementation more complicated.
Комментарии