TITAN-2 Completed Installation of Two Bridge Cranes at LNPP-2
OREANDA-NEWS. The work performed by the Holding's subsidiary Sosnovoborelektromontazh was performed at the first power unit of Leningrad NPP-2 turbine hall.
The two commissioned cranes have different load capacities: 15 and 50 tons. Another result of this week's work is the completed repair of a heavy-duty crane (load capacity 220 tons). These cranes are used to mount operational equipment and piping for the turbine hall.
At the same time, another subsidiary of the Holding, MSU-90, continues installation work in the same turbine hall. The workers are installing high and low pressure heaters, separator-reheaters, while the supply division is shipping in low-pressure cylinder bearings.
Reference information:
Holding TITAN-2 is the largest group of companies in the North-West Region, working in the construction of the most significant facilities for the nuclear power plants and power supply industry. Its organisations provide a full cycle of construction operations - from design of project documentation to delivery and commissioning. Exceptional work is ensured by over 4,000 highly qualified staff specialists across nearly 15 organisations with more than 40 years of experience in the construction of unique and especially complex facilities. The managing company and the core engineering business-unit of the Holding is CJSC CONCERN TITAN-2.
TITAN-2 is one of the main contractors involved in construction and installation works at the power units 1 and 2 of the Leningrad NPP-2. The company performs over 30% of all general construction and 80% of installation works. The holding's own specialists are involved at 42 sites of the 1st and 2nd power units of LNPP-2. The works involve operations with the reactor hall, turbine, power supply, water supply and other facilities of the power units.