MICEX Announced Migration of SPECTRA to M1 Data Center
OREANDA-NEWS. As part of technology infrastructure development strategy, the Moscow Exchange has planned to migrate SPECTRA platform to the M1 data center (125 Varshavskoe shosse, Moscow) which plays the role of the main Moscow Exchange data center. The migration should be completed by Q3 2013.
After the migration is completed, both Trading Platforms serving all Moscow Exchange markets will be consolidated in a single data center.
The SPECTRA platform migration maintenance followed by comprehensive functional and load testing by trade participants is scheduled to August,10 2013; the reserve date is set to August, 17. Please ensure your employee schedule covers these dates.
The Moscow Exchange would like to draw your attention that after the migration is complete, the market access through dedicated network channels will only be possible by the Universal connection scheme; internet connection scheme is kept intact.
Комментарии