Frame of Main Building Is Being Constructed at Izhevskaya TPP
OREANDA-NEWS. Heating loop of electrical rooms in the main building was closed, temporary heat was supplied. Installation of metal works for the turbine hall frame is coming to the end, the gas turbine generator and gas turbine unit were placed on to their design reference marks.
Currently, metal works of the main building turbine hall are being installed, wall panels are being erected, and power floors are being grouted in the turbine hall and boiler room.
Construction of the new CCPP was commenced in June 2012. Reliability run of the upgraded station is scheduled for the end of 2013, power certification procedure is to take place by April 1, 2014.
Комментарии