Foundation Concreting Completed at Cooling Tower of Novovoronezh II/2
OREANDA-NEWS. November 21, 2012. Circular foundation concreting has been completed at unit 2’s evaporative cooling power of Novovoronezh II, a 16 November report of Atomenergoproekt, the power plant construction general contractor, says.
“In the nearest time, the construction workers will begin to install reinforced-concrete structures to form, together with the foundation, the concrete cooling tower’s base”, the company reports.
The cooling tower of Novovoronezh II’s unit 1 has already been erected to the design height of 171 m.