Baksanskaya HPP Tested Hydro Unit No. 3
OREANDA-NEWS. October 30, 2012. Rakurs Group took part in testing of hydro unit No. 3 conducted at Baksanskaya HPP from September 28 to October 2.
The testing has been performed within the bounds of Rakurs Group complex works on designing, manufacturing, delivery and assembly of the equipment of HPP automated control system, equipment of information collection and transfer system and emergency events recorder for Baksanskaya HPP.
During the hydro unit idle running testing rotor rotation speed has been regulated, vibration characteristics and hydro unit hydro energetic parameters have been determined. In parallel with preparatory works for hydro unit No. 3 start up in the mode of idle running there have been continuing assembling works on the first and the second power units.
Rakurs Group is a leader in the sphere of designing of automated control systems for heat- and hydro power engineering objects. For more than 20 years of work a huge experience in industry automation sphere has been gained, a serious number of projects has been completed as for small objects as for large industrial complexe
Комментарии