OREANDA-NEWS.  October 04, 2012. The signing ceremony for the BT project of the northern section of Hengqin (Second Hengqin Bridge) on Jingang Road was held in Zhuhai, reported the press-centre of CCCC.   

With a total investment of 2.43 billion yuan, the project is Zhuhai’s first transport project constructed in the mode of BT, the new in-depth cooperation between CCCC and Zhuhai Municipal Government after the comprehensive development project in Hengqin New Area with a total investment of 38 billion yuan, as well as another technically complex landmark project in Zhuhai after high-profile Hong Kong-Zhuhai-Macao Bridge.

In two-way six-lane design, with a length of 6.8 kilometers and a width of 33.5 meters, the bridge consists of the south and north approach bridges and the main bridge. The main bridge is 100m+400m+100m steel-truss arc bridge with double arc rib, the widest of its kind in China.