First Hydroelectric Generator on Matkozhnenskaya HPP Started Working
OREANDA-NEWS. October 2, 2012. The specialists of JSC TGC-1 carry out the first test launches of renewed hydroelectric on Matkozhnenskaya HPP which is part of Vigsky Cascade.
The company's specialists test the operating status of the auxiliary systems of hydroelectric generator №1: oil pressure settings and emergency repair valves. After the end of regulation in mid-October the load will be set for the unit. Hydroelectric generator №3 is also being prepared for inclusion in the network. The second section of the board of own needs is operating already providing more reliable work of plant equipment.
All repair activities on Matkozhnenskaya HPP are held as scheduled. The region is provided with energy fully and and without interruptions.
Комментарии