OREANDA-NEWS. September 27, 2012. This week within commissioning works on “Poliom” Ltd were started trials of control equipment devices, installed on equipment of production on PPF processing, reported the press-centre of Titan.

Hydrotesting of columns, including input of water and check under pressure, were held in autumn of the last year. As yet one finished piping and heat insulation of columns, containers, heat exchangers and other equipment. This week after finishing of pneumo- and hydrotesting on pipelines of energy resources supply specialists of the enterprise get down to loading of catalysts and adsorbents into reactors and dehydrators, started commissioning works on control equipment devices. Specialists of company “Samson-Tuymen’” are participating in commissioning works. This company supplies regulating and multi-purpose valves, which are installed on the enterprise.

Final stage of commissioning on production on PPF processing will be testing on working media after receiving of production license by “Poliom” Ltd. Proper documents are due to be received by the enterprise management in the nearest future.

Production of propane-propylene fraction processing lies in the beginning of production cycle of the making of polypropylene. It supplies “Poliom” with feedstock – propylene distinguished for high degree of purity and concentration, necessary for the making of polypropylene.

The unit includes two reactors, heat exchanging and vessel equipment, three columns, two of them are almost 100 meters high. Capacity of the enterprise – 250 thousand tonnes of propane-propylene fraction per year.