Sesa Goa Limited Commissions Third Blast Furnace of 450 m3 Capacity
OREANDA-NEWS. August 23, 2012. Sesa Goa Limited ("Sesa or "the Company") is pleased to announce the successful commissioning of its third blast furnace of
The Company has also successfully completed the expansion of its metallurgical coke capacity from 0.28 mtpa to 0.56 mtpa along with the 30 MW waste heat recovery power plant.
The commissioning of the associated sinter plant of 0.8 mtpa capacity is also progressing as planned in line for commissioning in the current quarter.