TITAN-2 Keeps on Arrangement of Key Structural Elements at Baltic NPP
OREANDA-NEWS. July 30, 2012. Now construction of the foundation of under-annular corridor is getting closer to mark -7.50. The completion of the works will be a milestone in arrangement of the reactor's foundation at the first power unit of the Baltic NPP.
Along with that, the builders of TITAN-2 Holding organizations are completing the following types of work:
• Concreting the walls of security building from mark - 12.100 to - 9. 200;
• Reinforcing and concreting the foundation of administrative building from mark – 7.200 to – 6. 300;
• Reinforcing and concreting the floor structure of the drainage pumping plants;
• Arrangement of waterproofing layer at nuclear service building;
• Vertical and horizontal waterproofing of security building walls;
• Vertical waterproofing of reactor building.
The holding's subsidiary OJSC UAT is continuing its work related to arrangement of the spur railway track "
TITAN-2 Holding is the largest Group of Companies in the North-West of Russia which erects the most important facilities of nuclear industry and power engineering. It performs the full cycle of building and assembly works, from development of design documentation to the facility commissioning. The Holding consists of more than 15 organizations and employs about 4,000 employees with more than 40-year-experience in construction of unique and super-complicated facilities. The Holding’s management company and the leading engineering business-unit is the Company JSC CONCERN TITAN-2.
The Baltiyskaya NPP project implies construction of two power units with a 1,150 MW–reactor of WWER type and heating capacity of 250 Gcal each. The design-to-life cycle of Baltiyskaya NPP is 50 years, and that of the key equipment is 60 years. The first power unit is supposed to be commissioned in 2016, and the second one – in 2018. The station location is the north-east of the