Board of JSW Energy Approved Results for Quarter Ended June 30, 2012
OREANDA-NEWS. July 25, 2012. The Board of JSW Energy Ltd., at its meeting held at Mumbai, approved the Results for the quarter ended June 30, 2012.
Key highlights for Q1’ FY 13 (Consolidated):
• Highest quarterly net generation of 4,731 million units, growth of 95% over corresponding quarter of previous year
• Total Income from operations ' 2,192 crores, growth of 72 % over corresponding quarter of the previous year
• EBITDA of ' 660 crores, increase of 58% over corresponding quarter of the previous year
• Unit - 6 (135 MW) of Raj WestPower Limited (RWPL) synchronized on June 23, 2012
• JSW Energy awarded "Best Thermal Power Generation Company” at Power Line Awards, 2012
Operational Performance (Consolidated)
The operational performance for the quarter excelled with the Company, registering the highest quarterly net generation of 4731 million units, due to stabilised operations across all the locations.
The Plant Load Factor (PLF) achieved during Q1, FY 2012-13 were as under:
• Vijayanagar: The plant achieved average PLF of 101% as against 80% in the corresponding quarter of the previous year.
• Ratnagiri: The plant operated at an average PLF of 92%, against an average PLF of 65% in the corresponding quarter of the previous year.
• Barmer - The four operational units achieved an average PLF of 75%
The net generation from the different units were as under:
(figures in million units)
Location |
Q1, FY 12-13 |
Q1, FY 11-12 |
Vijayanagar |
1,745 |
1,385 |
Ratnagiri |
2,215 |
988 |
Barmer |
771 |
49 |
Total |
4,731 |
2,422 |
The merchant sales during the quarter were 2,498 million units, while the sales under the long term PPAs were 1,877 million units. During the quarter, 356 million units have been generated under the Conversion Agreement.
Fuel
Imported thermal coal prices corrected sharply during the course of the quarter due to weak global economy and spurt in thermal coal exports from US. However, the reductions in the imported thermal coal prices have largely been off-set due to steep depreciation in the Indian Rupee against US Dollar during the quarter. The benefits of the reduction in coal prices have only marginally been realised, as inventory at the beginning of the quarter have been fully consumed during the quarter.
The efforts to blend coal to reduce cost during the quarter have been encouraging with stable plant operations. The fuel cost during the quarter was ' 1,155 crore, an increase of 63% over the corresponding quarter of the previous year, primarily due to increase in power generation.
South African Coal Mining Holding (Pty) Ltd (SACMH):
During the quarter, SACMH mined 109,919 tonnes of raw coal from the existing underground mine. While an existing open cast mine got closed upon extraction of entire coal, approvals are awaited for commencement of open cast operations at a different location, resulting in significant reduction in coal production and higher costs. The total sale of coal during the quarter was 50,930 tons.
Financial Performance (Consolidated)
During the quarter, the Company achieved a Total Income from operations of ' 2,192 crore and EBITDA of ' 660 crore, primarily on the back of enhanced capacity. The Company has earned a Profit after tax of ' 3 crore during the current quarter against a Profit after Tax of ' 136 crore in the corresponding quarter of the previous year. The Profitability for the quarter is lower primarily due to net foreign exchange loss of ' 232 crore, considered as an exceptional item, due to the unusual and sharp movement in the value of the Indian Rupee against US Dollar.
Maharashtra Electricity Regulatory Commission (MERC) has granted approval for tariff petitions for FY 10-11 and FY 11-
Projects Update: a) Status of projects under Construction and Implementation
1,200 MW - at Ratnagiri
The commissioning of Unit-1 FGD has been delayed due to a major fire in the absorber tower on May 19, 2012. The Company has since revised the commissioning schedule of the FGD for all units, in phases between Nov ‘12 to Feb ‘13, pursuant to an approval from MOEF to the revised schedule.
1,080 MW - at Barmer
Unit 5 and Unit 6 of 135MW each at Barmer have been synchronised and work on the balance 2 units is progressing satisfactorily and is expected to be completed in quarter 2, 2012-
Work on obtaining necessary consents / approvals for 270MW expansion project at Barmer is in progress.
240 MW - at Kutehr, Himachal Pradesh (HP)
The Catchment Area Treatment (CAT) Plan has been approved by Government of Himachal Pradesh on April 4, 2012 and the same has been forwarded to Ministry of Environment and Forests (MoEF). The land acquisition process for the project is progressing satisfactorily, while necessary clearances are awaited. Project expenditure (including premium paid to state government) spent till June 30, 2012 is ' 143 crore.
Barmer Lignite Mining Co. Ltd (BLMCL).
During the quarter, BLMCL has supplied 841,770 tonnes of lignite to RWPL. The possession of land for Jalipa mines is expected to be provided shortly. The project cost is estimated at ' 1,800 crore (comprising of both Kapurdi & Jalipa mines) and cost incurred till June 30, 2012 is ' 1,245 crore.
(b) Projects under Development
1320 MW Chhattisgarh Project
The land acquisition for the project, initiated by Chhattisgarh State Industrial Development Corporation (CSIDC) is making steady progress with award for only one village awaited out of five villages. Design and engineering related to various aspects of the project are also on schedule and other necessary approvals are also being expedited.
Others
The work on developmental projects planned in
The global growth continues to be weak as developed countries try to combat recession and revive growth while developing countries look to address high inflation by curbing consumption. The challenges of the Euro Zone Sovereign debt crisis may further extend the recovery period. These global events have resulted in softening of the energy prices and the thermal coal prices have also moved in similar direction. The thermal coal prices have seen sharp reductions on the back of weak demand as also export of thermal coal from US (upon cheap Shale gas replacing thermal coal demand in US ). Domestically, controlling inflation remained the primary objective, which has impacted the growth primarily of the manufacturing sector. The global uncertainties and widening deficits have led to steep currency depreciation. The tariff revisions by distribution entities have been positive for the sector and are expected to improve fiscal position of distribution entities. Delay in resolution of issues surrounding fuel has impacted the ability of power plants to fully exploit the latent capacity. We expect government to resolve the issues critical to the sector; however, delay, if any, in resolution of issues is likely to ensure that demand for merchant power may remain robust during the said period.
Комментарии