OREANDA-NEWS. July 23, 2012. The cost of the project to be implemented by contracting OOO “Severgazavtomatika” will amount to about 124.9 mln RUR.
From August 1st, Vologdaenergo branch of IDGC of the North-West will start Investment Project related to construction of “Druzhba” 35/10 kV substation with 35 kV overhead line branch running to the Veliky Ustyug District, (Vologda Region) The cost of the project to be implemented by contracting OOO “Severgazavtomatika” will amount to about 124.9 mln RUR. “Druzhba” 35/10 kV substation will become a polygon to work out modular technology of substation construction.
The following works will be carried out on the energy facility: construction of the 35/10 kV substation and 35 kV two-circuit overhead line to connect the substation to existing 35 kV grids as well as construction of fiber-optic communication lines 27.5 km long to link the substation to the “Veliky Ustyug” head station 110/35/6 kV.
The new substation “Druzhba” will deliver electricity to the socially essential facilities of Veliky Ustyug District, including existing and new projects being built due to “Veliky Ustyug – Motherland of Ded Moroz” Program. They are Ice Palace, House of Ded Moroz, Entertainment Park.
Комментарии