BP Egypt Announces Seth First Gas
OREANDA-NEWS. July 05, 2012. First gas from the USD 334 million Seth development commenced approximately 18 months from project sanction, which is 15 weeks ahead of schedule.
Seth field is located 60km offshore in the Ras El Bar concession in the East Nile Delta Mediterranean, close to existing producing Ha'py and Denise fields. Seth is being developed with a 6 well slot, normally unmanned platform with gas being exported via the Denise (Pliocene) pipeline to El Gamil gas terminal near
"Seth is yet another example of BP’s 50 years of commitment to
“The success of the Seth project has led us to accelerate its Phase 2 development to access gas in the eastern part of the field through an additional two platform wells, which are planned to be on production by the end of 2012, increasing Seth offtake to in excess of 250 mmscfd,” added Mekawi.