Metinvest Revamps MMKI Heat Station -1
OREANDA-NEWS. June 27, 2012. At the first heat station of MMKI, which is a part of Metinvest Group, large-scale construction of turboblower № 3 was accomplished and it was commissioned at the 21 of June. It will allow to increase the productivity of blast furnace №3 to 7% and to reduce the specific consumption of coke to 7 kg/t of hot metal. The cost of the project is 31 mln USD .
Among the technological equipment of Heat Station -1 the turboblower №3 will be the most up-to-date. The 19th MW turbine and compressor with the production capacity
Taking into account that at present 8 air blowers are already working at the Heat Station -1, the technicians found the way to implement at the Works proven, efficient, high-power computerized turbine compatible with the already existing equipment.
“Commissioning of the new turboblower is only the first stage of the integrated programme of Works technological revamp up to