Perm Engine Company Manufactured Three Gas Turbine Plants
OREANDA-NEWS. May 24, 2012. OJSC "Perm Engine Company" in the framework of the contract with CJSC "Iskra-Avigas" manufactured three gas turbine plants GTU-10P for LLC "Gaspom dobycha Urengoy". All three Perm gas turbine plants with the unit power of 10 MW are intended for use as a drive comprised into the boosting compressor station (BCS) in the Central processing facility UKPG-8V Urengoy oil-gas condensate field (NGMK).
At the moment the boosting compressor station DCS-2V of LLC "Gasprom dobycha Urengoy" runs four Perm gas turbine plants of the same type and one standby engine. Other three GTU-10P В are now being mounted and commissioned at the analogue boosting compressor station DCS-5V. According to the contract for 2012 Perm Engine Company is to manufacture and deliver next 8 GTU-10P plants for another boosting compressor station in the different Central processing facility of Urengoy oil-gas field.