OREANDA-NEWS. May 10, 2012. "Krasny Kotelshchik" (main production site of JSC EMAlliance) has produced three assemblies for Boiler TP-100 of Burshtinskaya TPS (PJSC "Zapadenergo"). The weight of the control stage of the secondary superheater, the headers of the primary superheater and the panels of the wall-type radiant superheater amounted to 100 t.

 The Contract for conducting reconstruction and retrofitting works of boiler TP-100, power unit No.5 Burshtinskaya TPS, was signed by JSC EMAlliance and the Customer in November 2011. In accordance with the document, EMAlliance conducts the design works of 12 assemblies of the boiler, produces and supplies 7 assemblies with the weight of 350 t, as well as conducts installation supervision of the produced equipment in place of its operation.   

 The production manufacturer for Burshtinskaya TPS is Taganrog Boiler-making Works "Krasny Kotelshchik". The Company’s experts produced three assemblies from the planned seven assemblies. The remaining heating surfaces and headers are currently in progress. The shipment to the Customer is planned to be accomplished here in November-December 2012.    

 New equipment will help to increase the installed electric power of the power unit and decrease fuel unit consumption. 

 We remind you, that two years earlier Krasny Kotelshchik took part in the retrofitting of Burshtinskaya TPS Power Unit No.7. TKZ has produced four regenerative-type air preheaters RAH -54М2.