Works of Russian Personnel Resumed on Kudankulam NPP Site
OREANDA-NEWS. April 06, 2012. The works, which have been interrupted in October 2011 because of blocking of the personnel’s access to the site, are resumed on the site of Kudankulam NPP constructed with participation of JSC "Atomstroyexport", a company of the State Corporation "Rosatom".
Complete assessment of the equipment and definition of the list and schedule of the required works are currently performed. According to results of the assessment of the equipment, necessary works on adjustment of the main process equipment will be outlined, including the works on running of all main circulation pumps. A ultimate goal of these works is to finalize the stage of the second inspection of the equipment at Unit 1 and obtain permit from the Atomic Energy Regulatory Board of India (AERB) for fuel loading.
Joint-Stock Company "Atomstroyexport" (JSC ASE), for the fulfillment of the Intergovernmental Agreement, is performing works on construction of the first phase of Kudankulam NPP in
obligations includes according to the signed contracts: development of the Technical Design and working documentation, architectural supervision over construction of the NPP buildings and structures within the design scope, delivery of the equipment and materials from Russia and third countries, technical support during NPP erection and commissioning, training of the operation and maintenance personnel in Russia. The Customer – Nuclear Power Corporation of India Limited (NPCIL) – performs construction, erection and pre-commissioning works on the NPP site and also commissioning of the plant.
In 2011 the following key events were achieved at the commissioned Unit 1 of Kudankulam NPP:
• 15.01.2011 – the hydraulic strength tests of the primary and secondary circuits under the pressure of 250 kg/cm2 and 110 kg/cm2 accordingly were successfully carried out, the stage of hydraulic tests and circulation flushing was completed;
• 08.02.2011 – the stage of strength tests of the containment of Unit 1 was successfully completed;
• 30.06.2011 – the works of the stage of the first inspection of the equipment were completed;
• 06.09.2011 – the basic programs of the “hot run” stage were completed, the power unit was transferred to the cooldown mode with the subsequent transfer to the stage of the second inspection of the equipment.