Reconstruction of Berlin Bridge in Kaliningrad Held Ahead of Schedule
OREANDA-NEWS. March 27, 2012. The builders are prepared to open the
The bridge pillars are being erected around the clock on the construction site. Meanwhile the bridge builders are conducting preparations for installation of steel structures.
The 2012 work schedule includes bridge pillar erection and steel structure installation in spans 1 through 7 and 16 through 22, roadway slab completion in spans 1 through 7, and bridge approach roads embankment shoring with prismatic piles for 40% of design scope work scope.
The bridge total length is