NPO Saturn Delivered Its Customer 110 Megawatt GTD-110 Engine
OREANDA-NEWS. January 20, 2012. NPO Saturn has fully executed its 2011 plan of supplying high-power gas-turbine engines to INTER RAO UES OJSC. Today the company shipped off to its customer the high-power GTD-110 №7 generating 10 megawatts of power. This is a second high-power gas-turbine engine intended for completing the block №2 of the
At this moment there are three high-power industrial turbines manufactured by NPO Saturn put into industrial operation – two GTD-110 engines №3 and 4 operate as part of the block №1 of the Ivanovo combined-cycle power plant, one GTD-110 engine №5 – as part of the CCPP of the Ryazan state district power plant.
The GTD-110 № 6 after completing its commissioning tests at the
The pilot GTD-110 №2 having reached its MTBR being 25 000 hours is undergoing inspection at NPO Saturn to be subsequently overhauled by the company.
In the frame of implementing its high-power industrial turbine production program, NPO Saturn also carries out a number of actions aimed at enhancing operating performance and in-service reliability of the GTD-110 engine and is constantly working on improving its customer support network.
The GTD-110 engine project has been put on the list of the MC ODK prioritized programs, which guarantees its further development.