Zorya-Mashproekt Delivered Installations to Novonuksenitskaya Station
OREANDA-NEWS. January 18, 2012. Two 25MW gas turbine DU 80 engines were shipped to Novonuksenitskaya compressor station.
Construction of Novonuksenitskaya is the first phase of Gazprom’s project for the gas pipe-line building. The new gas pipe-line will supply gas from Bovanenkovo (Yamal Peninsula) to Torzhok (Tver Oblast).
The total power of compressor station is 100MW. The new compressor station will be equipped with four ГПА-25 plants. The compressor station construction will be completed in the second quarter of 2013.
Since June 2012, gas pipe-lines Bovanenkovo - Ukhta - Torzhok and Nothern Regions of Tyumen Oblast - Torzhok will be inputted into service. In addition to two 25MW engines for Novonuksenitskaya, Zorya-Mashproekt delivers 25 MW plants to the compressor station in Bovanenkovo.
Gazprom carries out the natural gas extraction in Yamal and forms a new generation of gas transportation system, which will transmit the additional gas volume to the customers in Russia and abroad. Thus, Zorya – Mashproekt makes a contribution to Gazprom’s projects development.
Комментарии