Polyus Gold Announces Commissioning of Mining and Processing Facility
OREANDA-NEWS. January 5,
Construction of the facility commenced in 2009 and involved the Company’s specialists building a gold extraction plant on a
During the first half of 2012 the process plant is expected to operate using a flowsheet that provides for gravity concentrate generation at an ore grinding circuit with subsequent final processing to end product at the existing process plant at Zapadnoye.
During the second half of 2012, upon installation of flotation and hydrometallurgical equipment, Polyus intends to commence operation of the Verninskoye mining and processing facility using design gravity and flotation flowsheet with base gold production directly at the process plant.
During the construction, the Company continued active exploration of the flanks and deep levels of the Verninskoye deposit. In 2010 an audit of the mineral resources base at Verninskoye resulted in an increase of proved and probable reserves to 65.4 million tonnes of ore or 5.8 million ounces(179.0 tonnes) of gold. This increase in reserves allows for the possibility of expanding the process plant throughput capacity to deliver increased gold output of 3.6 million tonnes per annum. The Company is currently estimating options for development of an extended pit.
“Commissioning of this new mining and processing facility in the
“In the beginning of 2012 the plant will operate in start-up mode ramping up to design throughput capacity in H2