First Four Houses of “Minsk-City” Complex Are Ready to Be Accepted
OREANDA-NEWS. December 27, 2011. The first four houses in multifunctional complex “Minsk-City” will be ready to be accepted by the State Committee at the end of 2011. The ITERA International Group of companies acts as the project investor.
The new buildings are located within Ulitsa Aerodromnya and 2-d Germanovsky Pereulok. These are two M111-90-series 19-storey residential buildings and two M111-90 and M464-9-U1 series 10-storey 4-section slab apartment houses. In aggregate, the buildings have 615 apartments, including 1, 2, 3 and 4-room apartments of 37 to
Currently, external and internal heat and water supply systems are at the stage of completion, and drainage network system is completed. Exterior and interior finishing of the houses as well as sanitary engineering and electric installation work are at the final stage.
The preparation of the residential buildings for acceptance is in parallel with class "B" office premises reconstruction. The quarter’s territory step-by-step development is scheduled for 2012-2014, including construction of ten more residential houses, a shopping center, multi-level parking lots, kindergartens and other infrastructure facilities.
According to Vladimir Aleksandrьvich, the Head of ITERA Group development projects in
The ITERA Group is a vertically integrated holding company, one of the major independent natural gas producers and sellers in
The ITERA Group development business is represented with large construction projects, including "Minsk-City" Business Center with the first residential skyscraper "Parus" in the Belarusian capital, a hotel complex in Avaza resort area in Turkmenistan, office premises for the Organizing Committee of the 2014 Olympic and Paralympic Games in Sochi, "Pavlovy Ozera" cottage settlement in Moscow Region and other projects.