KEGOC Held Public Hearings in Ust-Kamenogorsk
OREANDA-NEWS. December 12, 2011. KEGOC held the public hearings in
The representatives of mass media, Akimat of East-Kazakhstan Province, housing and public utilities divisions, passenger transport and motor roads of Beskargai, Ulan and other regions of the Province, labor veterans and interested public members participated in the hearings. The representatives of the structural divisions of KEGOC presented the projects. Earlier the public hearings on the project were successfully held on November, 18 of the current year in Ekibastuz.
The hearings on the project are held in accordance with the requirements of environmental legislation of the
Currently the power connection of
From the administrative point of view the OHTL route is designed at North-East within
According to Preliminary EIA the designed substations and 500 kV and 220 kV OHTLs are located outside the specially protected natural areas.
Environmental protection measures used during the construction of 500 kV and 220 kV OHTLs, construction and expansion of substations are intended to minimize the impact on the environment.
The cost of the project is KZT 42.5 billion, implementation period – 2011-2017. The financing is expected to be from the attracted borrowings and own funds of KEGOC.