Essar Steel Commissions Second Conarc Furnace
OREANDA-NEWS. December 1, 2011. Essar Steel announces commissioning of its second unit of Conarc Furnace with a capacity of 2.5 MTPA, taking total capacity of steel melt shop to 5 million tonnes. With the commissioning of this furnace, Essar Steel has commissioned all steel making units, iron making and rolling units that are part of 10 million tonne expansion project barring a Corex unit which is slated for commissioning later this year.
This will be
The Conarc Furnace will be fed with inputs from Blast Furnace with a capacity of 1.73 MTPA (already commissioned), DRI with a capacity of 1.74 MTPA (already commissioned) and 2 Corex units of 0.87 MTPA of which one is already commissioned and the second unit is scheduled to commissioned in December this year.
Essar Steel has installed continuous caster of 1.45 MTPA. In addition, Compact Strip Production mill (CSP) of 2.5 MTPA has also become fully operational. The CSP is capable of producing strips of thickness as low as
In addition, Essar has also invested in various supporting infrastructure at Hazira that include power plants of 1015 MW and a all-weather port of 30 MTPA at total investment of over Rs.5000 crores.
Комментарии