Executive Director of Yenisei TGC Summarized Five Years of Operations
OREANDA-NEWS. November 30, 2011. The 2011 Second Siberian Energy Forum comes to a close in
Evgeniy Zhadovets, Executive Director of JSC “Yenisei TGC (TGC-13)”, spoke at the plenary session, Efficient Energy – Key Driver towards Economy Modernisation, on 16 November.
In his speech, he summarised the company’s operations since it was launched five years ago.
“Yenisei TGC” was set up on 31 December 2006 as the generation assets of
Over five years, from 2007 to 2011, the energy company has allocated over 18,700 million roubles for the purpose of renovating energy facilities, including 12,600 million roubles for new construction. During this period, “Yenisei TGC” generated over 50 billion kWh of electricity and supplied over 70 million Gcal of heat. Taxes paid to various budgets and extrabudgetary funds exceeded 8 billion roubles, out of which about 3 billion roubles were contributed to the budget of
As Evgeniy Zhadovets underlined,
“"Yenisei TGC" was established during the reform of the national energy industry,” Evgeniy Zhadovets said, “and our company, like other generators in the country, is now private. There are both advantages and disadvantages to this. I should note that the company has made advances over the post-reform period. As one of the achievements, the security of heat supply was increased. There has been no break throughout main heat systems over the last three years.
The number of equipment failures decreased significantly.
The company has been consistently repairing and renewing its fixed assets. In particular, “Yenisei TGC” has replaced
“Yenisei TGC” has also been implementing a large-scale investment programme. Two projects have already finished with a turbine reconstructed at Minusinsk CHP and a turbine set reequipped at Kansk CHP. Power unit 1 is about to be finished at Krasnoyarsk CHP-3 where individual testing of thermal and electrical equipment is already being conducted. Furthermore, other two power delivery projects have been launched – the renewal of power unit 7 has begun at Nazarovo GRES and preparation work is being done before the construction of a new unit at Abakan CHP.
“Our efforts give a huge impetus to further development of