TGC-2 Carried Out Tests of Open-Type-Bus-Switch Arrangement 330 kW
OREANDA-NEWS. November 25, 2011. New energetic block building on
Open-type-bus-switch arrangement test was carried out within investment project realization - steam-gas plant 210 megawatt building. The project is realizing within the Agreement of power delivery. The document preparation for permission commissioning receipt is happening at present.
The saltworks installation is completed on the site of Novgorod TEC. There is a setup of electrical equipment on local panel in hand of Czechia specialists. Saltworks efficiency would be
Construction of project steam-gas plant on Novgorod TEC would increase plant capacity from 200 to 350 megawatt and comply with necessity of electric energy in V. Novgorod on 100% and 70% of