HRT Released Monitoring of Well Drilling
OREANDA-NEWS. October 31, 2011. HRT Participacoes
Well 1-HRT-1-AM
The formation tests continue to be carried out in the intervals of interest.
Well 1-HRT-2-AM Current depth: 3,421m.
Drilling the 4th phase*, in the zone of interest (Uere Formation), forecasted till the depth of 3,600m.
Well 1-HRT-4-AM Current depth: 2,311m.
It was performed the intermediate logging and the well is being prepared to run the 95/8' casing.
Zone of interest forecast for depth between 2,320m and 2,700m. Well 1-HRT-5-AM
The QG IX rig was dissembled at the well 1-HRT-3-AM and it is being transported to Block SOL-T-192, to be assembled at the location 1-HRT-192/01.
[1] 4rd Phase: Drilling, logging, running the 7'' liner, cementing and doing the production test.