RusHydro Increased Electricity Generation by 5% in 9 Months of 2011
OREANDA-NEWS. October 26, 2011. RusHydro Group (ticker symbol: RTS, MICEX, LSE: HYDR; OTCQX: RSHYY) announces the operating results for the 3rd quarter and 9 months of 2011.
The Group's total electricity generation in the 9 months of 2011 amounted to 59,213 GWh - an increase of 5.3% compared to the same period of
3Q and 9M 2011 electricity generation (GWh)
|
3Q2011 |
3Q2010 |
chg,% |
9M2011 |
9M 2010 |
chg,% |
|
2 857 |
3 285 |
-13 |
9 271 |
10 363 |
-11 |
|
5 804 |
4 508 |
29 |
16 530 |
9 416 |
76 |
Sayano-Shushenskaya HPP |
5 291 |
3 712 |
43 |
15 003 |
7 543 |
99 |
Center |
8 727 |
7 924 |
10 |
27 431 |
28 814 |
-5 |
South and |
2 348 |
2 310 |
2 |
5 378 |
6 992 |
-23 |
|
212 |
178 |
19 |
600 |
658 |
-9 |
RusHydro Group |
19 948 |
18 205 |
10 |
59 213 |
56 244 |
5 |
The main factors behind the generation growth were the reconstruction of 4 out of 10 hydro-units of the Sayano-Shushenskaya hydropower plant that had been damaged during the 2009 accident as well as rationalization of water use of reservoirs.
January-September of 2011 was marked by subnormal water levels in European Russia and Far Eastern region. Initial forecasts made by the Hydrometeorological Center of Russia in early 2011 on increased water accumulation in snow packs didn't materialize; water inflows were lower or similar to average long-run.
The total electricity generation of RusHydro's hydropower plants in
In the 1st quarter of the year,
In the 3rd quarter, the water regime of the Sayano-Shushenskoye reservoir was established with account to reservoir filling intensity set by Lenhydroproject, change of controlled hydrotechnical parameters, transportation of major hydropower equipment for the continuing reconstruction of the Sayano-Shushenskaya power plant by river and pre-commissioning test runs of the onshore spillway. The maximum replenishment of the Sayano-Shushenskoye reservoir in 2011 was
According to the forecasts by the
In the 9 months of 2011, electricity generation in the
In European Russia, unprecedented heat and decreased water inflow in in the second half of 2010 resulted in 23% decrease of reservoir levels relative to long-term average. In the 1st quarter of 2011, the water inflow was lower compared to previous years but exceeded the long-time annual average by 5%. In the second half of 2011, the water inflow figures were 18% lower than normal.
To implement water saving policy, the
As a result of water saving policy the replenishment of reservoirs by the end of the 3rd quarter was only 2.5 km3 less than long-term average, but exceeded last year's levels by 8.6 km3, which may result in 4th quarter electricity generation close to normal levels. In the 1st quarter of 2012, electricity generation is likely to higher year-on-year.
Rationalization of water use during the 9 months of 2011 led to electricity generation of hydropower plants of RusHydro Group in the central regions of European Russia in the amount of 27,431 GWh which is only 5% less than in 2010. Increased water levels of Volga-Kama reservoirs (5-7% above last year) enabled a surge of 10% in electricity generation in central
The total inflow of water in the reservoirs of Volgo-Kama basin is forecasted to be 29-37 km3 with normal levels at 36.6 km3.
South and
Hydrological situation in North Caucasus and
Sevan-Hrazdan cascade of seven hydropower plants in